If a project includes any actions listed in Hawaii Revised Statutes Section 343-5, compliance with the State’s environmental review process is required. To complete the process, either:
The State or county agency that initially receives and processes an application for a discretionary approval is the agency that processes the environmental impact statement. If the Department of Planning and Permitting (DPP) is the approving agency, follow the general steps below, and refer to our EIS Instructions for more detailed information.
Complete all of the required documentation for the Environmental Impact Statement Preparation Notice (EISPN). Starting August 4, 2025, all permit applications must be submitted to the DPP through HNL Build. However, there is currently no application type for the submittal of EAs or EISs in the HNL Build system. Therefore, until such time as this function becomes available a single electronic .pdf application package should be emailed or submitted in person to DPP as follows:
Submit two checks or money orders made out to the City & County of Honolulu for:
Submit two checks or money orders made out to the City & County of Honolulu for:
Submit two checks or money orders made out to the City & County of Honolulu for:
Checks or money orders that are more than 3 months (90 days) old will not be accepted. There is no fee for City agencies.
The fees are doubled when an applicant applies for a permit after being cited for taking action without obtaining necessary approvals.
Fee payments are not accepted online and must be delivered to:
Department of Planning and Permitting
650 South King Street, 7th Floor
Honolulu, HI 96813
The DPP submits the EISPN to the State’s Environmental Review Program for publication in the next edition of The Environmental Notice, which initiates a 30-day public comment period.
Following the 30-day comment period, the applicant must prepare and submit a draft EIS that incorporates all written comments received and responses to those comments, as well as a summary of the required EIS public scoping meeting.
The applicant must submit the draft EIS to both the DPP and to the State’s Environmental Review Program for publication in the next edition of The Environmental Notice, which initiates a 45-day public comment period.
Following the 45-day comment period, the applicant must prepare and submit a final EIS that incorporates all written comments received and responses to those comments to both the DPP and to the State’s Environmental Review Program for publication in the next edition of The Environmental Notice.
The DPP determines acceptance or non-acceptance within 30 days.
If the DPP does not make a determination within 30 days, the final EIS is deemed accepted. Acceptance and non-acceptance determinations are subject to a judicial challenge period, pursuant to HRS Section 343-7.
For more information on the EIS process, please contact the DPP at (808) 768-8000 or email dpp@honolulu.gov.
A webpage of the City and County of Honolulu, supported by the Hawaiʻi Office of Planning and Sustainable Development, Coastal Zone Management Program, pursuant to National Oceanic and Atmospheric Administration Award, Award No. NA18NOS4190082, funded in part by the Coastal Zone Management Act of 1972, as amended, administered by the Office for Coastal Management, National Ocean Service, National Oceanic and Atmospheric Administration, United States Department of Commerce.