Major SMA Permit
A Major SMA Permit (also know as an SMA Use Permit) is required for “development” (as defined in Revised Ordinances of Honolulu Chapter 25) within the SMA that has a total valuation of more than $500,000, or that may have substantial adverse or cumulative impacts. For information about what the SMA is and whether a property is within the SMA, visit our Coastal Area Permits page.
As explained below while preparing a Major SMA Permit, please use our fillable PDF. The below is a summarized version of instructions. There is a checklist to confirm that the application is complete.
Any change to a Major SMA Permit that does not have a significant effect on coastal resources may be processed as a Minor Modification.
An SMA permit is required for “development,” which includes any construction, grading, or change in the intensity of the use of land, with certain exceptions. Generally, those exemptions include:
If you aren’t sure whether an SMA permit is required, you can submit an SMA Permit Determination request form under Coastal Permits in HNL Build.
Hawaii Revised Statutes (HRS) Chapter 343: If the Project requires environmental disclosure documentation under HRS Chapter 343, a complete application for an SMA Major Permit must contain documentation that the potential environmental impacts associated have been evaluated and publicly disclosed in accordance with the regulations and guidelines published by the Office of Planning and Sustainable Development, Environmental Review Program. Documentation may include an HRS Chapter 343 Exemption Notice, published a Final Environmental Assessment (EA) and Finding of No Significant Impact, or a published Final Environmental Impact Statement (EIS) and Notice of Acceptance from the accepting authority. This documentation should be uploaded into the “Environmental Documentation” tab on HNL Build.
Note: If the project involves a prior EA or EIS upon which an exemption from the requirements of HRS Chapter 343 was based, and the Applicant does not anticipate that a supplemental assessment is necessary, then the Applicant must provide its written justifications explaining how the project has not substantially changed in size, scope, intensity, use, location, timing, or other means; or, if it has substantially changed, then how the change(s) do not involve significant effects.
Before applying:
Several documents must be uploaded before review can proceed. Upload all necessary files separately under the appropriate category on HNL Build.
Complete the Fillable SMA Major Permit Application Form: In lieu of other Written Statement documents, complete this form to provide a written explanation detailing all proposed activities and development, describe the existing conditions, evaluate the project’s compliance with the objectives, policies, and guidelines outlined in ROH § 25-3.1, and provide an analysis of the project’s consistency with the permit review guidelines outlined in ROH § 25-4.1. The Exhibits should be submitted as pdfs. Do not put the exhibits inside the fillable SMA Major Permit Application Form pdf.
Note that some sensitive issue areas require site-specific technical support studies, outreach to responsible agencies, and/or literature reviews in order to adequately evaluate the proposals consistency with ROH §§ 25-3.1 and 25-4.1.
Neighborhood Board Presentation Documentation: To prove the Neighborhood Board requirements have been satisfied, the permit application must include a signed, notarized affidavit, or similar document, confirming that adjoining property owners were sent written notification of the required neighborhood board presentation. Notes, minutes, or other documentation from the neighborhood board or community association summarizing the discussion should be included in the application materials.
Drawings/Plans: The application must include drawings and/or plans showing, at a minimum, the proposed site plan, and elevation drawings showing both proposed structures and the underlying grade and foundation components in relation to the overall site boundaries and site elevation. Where applicable, include revisions to any plans previously submitted during the EA or EIS review.
For shoreline lots, a site plan must showing the location of the certified shoreline, the shoreline setback line, the 3.2-foot SLR-XA (if applicable), the 1.1-foot, 2.0-foot, and 3.2-foot SLR-XA coastal erosion redline (if applicable) as shown on the Hawaii Sea Level Rise Viewer, and the boundaries of any flood hazard area (if applicable). If resilience and/or other coastal hazards adaptation measures are proposed as mitigation against coastal hazards impacts, the plans must also include elevation and/or foundation drawings showing the same information.
Note: See additional drawings/plans requirements on the SMA Major Permit Checklist below. All scaled plans and drawings must include a graphic (“bar”) scale in addition to or in lieu of a written scale.
Supplemental Information: Submit the following supplemental information, if applicable:
SMA Major Permit Application Checklist: The Applicant must complete and upload the checklist by marking all items that have been completed and/or included in the SMA Major Permit Application. For items that are not applicable to the proposed action, indicate “N/A.”
Fees may be paid online in HNL Build in “outstanding fees”. The review fee must be paid in order to complete the application submission. Alternatively, fees may be paid by check. If paying by check, submit two checks or money orders made out to the City & County of Honolulu for:
Checks or money orders that are more than 3 months (90 days) old will not be accepted. There is no fee for City agencies.
The fees are doubled when an applicant applies for a permit after being cited for taking action without obtaining necessary approvals.
If paying by check or money order, mail or drop off fee payments to the
Department of Planning and Permitting
650 South King Street, 7th Floor
Honolulu, HI 96813
5. Review
The DPP reviews the application, holds a public hearing, and makes a recommendation to the City Council.
The Honolulu City Council must deny or approve the application through the passing of a resolution within 60 calendar days of receiving the DPP’s report and recommendation. A copy of the approved resolution is then mailed to the applicant. Resolutions can be tracked on the City Council’s Records Collection website.
A webpage of the City and County of Honolulu, supported by the Hawaiʻi Office of Planning and Sustainable Development, Coastal Zone Management Program, pursuant to National Oceanic and Atmospheric Administration Award, Award No. NA18NOS4190082, funded in part by the Coastal Zone Management Act of 1972, as amended, administered by the Office for Coastal Management, National Ocean Service, National Oceanic and Atmospheric Administration, United States Department of Commerce.