Minor SMA Permit
Approval of an SMA Minor Permit is determined by the Director of DPP when development has a valuation which is not in excess of $500,000 for shoreline lots, or $750,000 for non-shoreline lots, and which has no substantial adverse environmental or ecological effect on SMA resources, taking into account potential cumulative effects. See ROH § 25-5.2. Note: Projects with a valuation in excess of $500,000.00 or which may have substantial adverse or cumulative effects must be processed as an SMA Major Permit.
While preparing a Minor SMA Permit, please use our fillable PDF. The below is a summarized version of instruction. There is a checklist to confirm that the application is complete.
An SMA permit is required for “development,” which includes any construction, grading, or change in the intensity of the use of land, with certain exceptions. Generally, those exemptions include:
If you aren’t sure whether an SMA permit is required, you can submit a SMA Permit Determination request form under Coastal Permits in HNL Build.
Hawaii Revised Statutes (HRS) Chapter 343 Environmental Disclosure Documentation
If the Project requires environmental disclosure documentation under HRS Chapter 343, a complete application for an SMA Minor Permit must contain documentation that the potential environmental impacts associated have been evaluated and publicly disclosed in accordance with the regulations and guidelines published by the Office of Planning and Sustainable Development, Environmental Review Program. Documentation may include an HRS Chapter 343 exemption notice, published a Final Environmental Assessment (EA) and Finding of No Significant Impact, or a published Final Environmental Impact Statement (EIS) and Notice of Acceptance from the accepting authority. This documentation should be uploaded into the “Environmental Documentation” tab on HNL Build.
Note: If the project involves a prior EA or EIS upon which an exemption from the requirements of HRS Chapter 343 was based, and the Applicant does not anticipate that a supplemental assessment is necessary, then the Applicant must provide its written justifications explaining how the project has not substantially changed in size, scope, intensity, use, location, timing, or other means; or, if it has substantially changed, then how the change(s) do not involve significant effects.
Application Contents Several documents must be uploaded before review can proceed. Upload all necessary files separately under the appropriate category on HNL Build.
Complete the fillable SMA Minor Permit Application: In lieu of other Written Statement documents, complete this form to provide a description detailing all proposed activities and development, describe the existing conditions, evaluate the project’s compliance with the objectives, policies, and guidelines outlined in ROH § 25-3.1, and provide an analysis of the project’s consistency with the permit review guidelines outlined in ROH § 25-4.1.
Note that some sensitive issue areas require site-specific technical support studies, outreach to responsible agencies, and/or literature reviews in order to adequately evaluate the proposals consistency with ROH §§ 25-3.1 and 25-4.1.
Project Valuation: A complete application for a SMA Minor Permit must include a detailed project valuation, which is the estimated cost of the project, as outlined in DPP Rules 20-31-6.
Note: The final determination regarding the project valuation will be made by the Director of the DPP. “Valuation” means the estimated cost to replace the structure in kind, based on current replacement costs; or, in the case of other development, as the current fair market value and prevailing wages relevant to the proposed development. All submitted estimates shall be prepared and signed by an impartial third-party licensed contractor or professional estimator; and, as the project valuation estimate approaches the $500,000 or $750,000 threshold (as applicable), greater precision in calculating the estimate shall be necessary.
Drawings/Plans: The application must include drawings and/or plans showing, at a minimum, the proposed site plan, and elevation drawings showing both proposed structures and the underlying grade and foundation components in relation to the overall site boundaries and site elevation. Where applicable, include revisions to any plans previously submitted during the EA process.
For shoreline lots, a site plan must showing the location of the certified shoreline, the shoreline setback line, the 3.2-foot SLR-XA (if applicable), the 1.1-foot, 2.0-foot, and 3.2-foot SLR-XA coastal erosion redline (if applicable) as shown on the Hawaii Sea Level Rise Viewer, and the boundaries of any flood hazard area (if applicable). If resilience and/or other coastal hazards adaptation measures are proposed as mitigation against coastal hazards impacts, the plans must also include elevation and/or foundation drawings showing the same information.
Note: See additional drawings/plans requirements on the SMA Minor Permit Checklist below. All scaled plans and drawings must include a graphic (“bar”) scale in addition to or in lieu of a written scale.
Supplemental Information: Submit the following supplemental information, if applicable:
SMA Minor Permit Application Checklist: The Applicant must complete and upload the checklist by checking off all items that have been completed and/or included in the SMA Minor Permit Application. For items that are not applicable to the proposed action, indicate “N/A.”
Fees may be paid online in HNL Build in “outstanding fees”. The review fee must be paid in order to complete the application submission. Alternatively, fees may be paid by check. If paying by check, submit two checks or money orders made out to the City & County of Honolulu for:
Checks or money orders that are more than 3 months (90 days) old will not be accepted. There is no fee for City agencies.
The fees are doubled when an applicant applies for a permit after being cited for taking action without obtaining necessary approvals.
If paying by check or money order, mail or drop off fee payments to the
Department of Planning and Permitting
650 South King Street, 7th Floor
Honolulu, HI 96813
4. Review
The DPP will notify the applicant within 10 working days of the completed application submission the status of the application (i.e. application is accepted or determined to be incomplete). Within 45 days from the receipt of the completed application, DPP renders a decision.
The development project is approved or denied a Minor SMA permit. Decisions are communicated via HNL Build to the email address provided.
Any party wishing to appeal the Director’s action must submit a written request for a contested case hearing to the DPP within 30 calendar days from the date of mailing, personal service, or publication of the action of the Director. Contested case hearings are conducted pursuant to the Administrative Rules for Shoreline Setbacks and the Special Management Area (Title 20, Chapter 31).
A webpage of the City and County of Honolulu, supported by the Hawaiʻi Office of Planning and Sustainable Development, Coastal Zone Management Program, pursuant to National Oceanic and Atmospheric Administration Award, Award No. NA18NOS4190082, funded in part by the Coastal Zone Management Act of 1972, as amended, administered by the Office for Coastal Management, National Ocean Service, National Oceanic and Atmospheric Administration, United States Department of Commerce.
The views expressed herein are those of the author(s) and do not necessarily reflect the views of NOAA or the U.S. Department of Commerce.