King Street and Hotel Street
Road Rehabilitation Project
About the Project
The Rehabilitation of Streets Project (Unit 65D) will improve concrete pavement conditions, such as bus lanes, in key downtown areas.
Project Scope
Spot reconstruction within concrete bus lane, resetting/reconstruction of curbs, and the restoration/installation of vehicle detector loops and pavement markers, striping and markings.
Project Schedule
The work is anticipated to commence at the end of 2026 or early 2027 with construction expected to last approximately one year.
Project Locations:
- North King Street: Liliha St / Dillingham Blvd → North King St Bridge No. 1 (over Nuʻuanu Stream)
- South King Street: Bethel St → Alapa‘i St / South St
- Hotel Street: River St → Richards St
Map showing the project limits (highlighted in orange)
Community Noise Variance
The City requested a noise variance from the State Department of Health to allow construction activities to exceed maximum permissible sound levels outside of normal permitted hours. The request was approved after the City completed all required public notification procedures. A public meeting was held on October 9, 2025, and businesses and residents within the project area were notified and provided an opportunity to submit public comments.
The proposed nighttime work will help reduce traffic impacts and shorten the overall project duration, thereby minimizing long-term disruption to nearby residents and businesses.
Lane Closures & Bus Detours
Work is expected to take place during the day, but the contractor will be allowed to work at nights and weekends to condense the overall project timetable. While lane closures are expected during the work, we will be working closely with the contractor to minimize disruptions. We will also be coordinating with the Department of Transportation Services for any necessary lane closures and detours for buses.