Department of Design and Construction

Queen’s Beach Promenade Restoration Project

The Queen’s Beach Promenade Restoration Project has been recognized for its outstanding achievement in civil engineering. Completed in June 2025, the project restored a 100-foot segment of the Queen’s Surf seawall—part of a vital 2,000-foot stretch of Waikīkī’s longest continuous shoreline walkway that links Kūhiō Beach Park to the Waikīkī Aquarium. The repairs addressed existing structural damage and helped prevent further deterioration of the seawall and promenade. Today, the promenade once again offers ocean access, exercise, sightseeing, sunset watching, and photography opportunities. 
Restored Queen's Beach walkway on a sunny day showing the newly installed walkway. The beach is on the right the walkway on the left. A tall tree is overhead on the far left. Three individuals are walking on the walkway and another is walking on the grass. Barefoot Cafe is next to the grassy area and blue and brown umbrellas shading tables.

Restored section of Queen’s Beach walkway and seawall.

Project Background

On March 22, 2024, DDC reported that the seawall had sustained severe damage, undermining the promenade. The engineering team responded quickly by conducting an initial investigation and determining the necessary regulatory requirements. Unfortunately, the promenade catastrophically collapsed on May 28, 2024, further degrading its condition and obstructing access for a thorough investigation.

With design support from MKE Associates LLC, Geolabs, INC., and Sea Engineering, repairs to the promenade and seawall were designed, permitted, and successfully completed before the next summer swell season. The project team effectively addressed the public health and safety hazard, fully restoring the seawall and promenade to their intended function.

Project execution was critical, as the team encountered numerous unforeseen conditions during construction. This required rapid and efficient problem-solving to address public safety concerns and meet the urgent completion timeline. The promenade reopened to the public on June 13, 2025, restoring vital shoreline access to this heavily used area. This project exemplified how a rapid, well-coordinated response can effectively address an emergency situation. The many challenges faced and overcome made the Queen’s Beach Promenade Restoration project particularly rewarding and impactful.

Collapsed walkway. The pathway can be seen in the foreground with the collapsed walkway ahead, on a sunny day.

Collapsed walkway at Queen’s Beach

Project Approach & Challenges

The extent of the initial damage limited the ability to assess subsurface conditions. The team advanced with a plan to verify site conditions during construction and adjust repair techniques as needed.

A crane truck was used to place two-ton bags of beach-quality sand to form a cofferdam, lifting the bags over a large banyan tree to avoid impacts to the tree and a nearby café. BMPs were installed to provide a safe working environment.

To increase durability and reduce future maintenance, the project utilized duplex stainless-steel reinforcing within the concrete. The finished promenade features stamped concrete designed to replicate the original flagstone pattern. Supersacks of clean sand were staged to control turbidity and, after the project was completed, the sand was redistributed onto the beach.

Aerial image showing the installation of BMPs at the project site with a crane.

BMPs are installed to provide a safe working environment at the project site. 

Award Recognition

The Queen’s Beach Promenade Restoration Project earned the prestigious title of Best Medium Project at the American Society of Civil Engineers (ASCE) Hawai‘i Section – 2025 Outstanding Civil Engineering Achievement Awards, honoring the dedication of a skilled team committed to restoring a cherished public resource. The revitalized promenade enhances the Waikīkī experience for both residents and visitors, ensuring safe shoreline access for years to come.

Six individuals of varying heights in front of a white banner with a blue logo imprinted on it. A female is on the far left; the tallest male is next to her, and a shorter male next to him holds the award (a clear trapezoid-shaped one). On his right is a shorter female, next to two taller male individuals.

Project Team (left to right):  Jillian Sumitomo (MKE Associates LLC-structural engineer), Patrick Noll (DDC CMB Section A Chief [TA] /Civil Engineer IV), David Smith (Sea Engineering, Inc-Design), Elaine Morisato (DDC Supervising Project Manager), Jeff Remily (SEI-Construction), Alika Brown (SEI-Construction)

ASCE 2025 Award - Best Medium Sized Project. Oueen's Beach Promenade Restoration Waikiki, Oahu Department of Design and Construction,

2025 ASCE Award for Best Medium Project – Queen’s Beach Promenade Restoration at Waikīkī, Oʻahu

The Queen’s Beach Promenade Restoration Project was awarded the prestigious title of Best Medium Project at the 2025 Outstanding Civil Engineering Achievement Awards. This accolade highlights the collective efforts of a dedicated team focused on restoring a cherished community resource that promises to enhance the Waikīkī experience for both residents and visitors alike.