North Kalāheo Ave. Bridge rehabilitation Project

North Kalaheo Avenue bridge on a cloudy day. Heavy equipment is stationed and operating on one side of the bridge. Grass is in the foreground, and on the other side of the bank, trees and homes are in the distance - a "Sidewalk Closed - Use other side" Sign appears in the bottom right corner.

North Kalaheo Avenue Bridge

About the Project

The rehabilitation project for North Kalāheo Avenue Bridge No. 445 over the Kawainui Canal in Kailua is scheduled to run from March 30, 2026, and continue for approximately seven months through October, weather and site conditions permitting. Work will include repairing concrete delamination, spalls, and cracks on the existing bridge structure; constructing new sheet pile retaining walls behind each bridge abutment; and replacing bridge railings, the bridge deck wearing surface, drain pipes, and approach guardrails. These improvements are intended to strengthen the bridge’s structural integrity, extend its service life, and enhance safety for motorists, bicyclists, and pedestrians.

Work Hours and Traffic Impacts

We are committed to minimizing traffic’s impact on the community and will make adjustments to the traffic control plan wherever possible. As the project progresses, the schedule remains subject to change due to weather and unforeseen conditions. 

August – September Update

The special traffic control during the next three phases of the project will require an extended daytime contraflow and an overnight Kailua-bound detour.

In response to community feedback, the daytime contraflow has been extended from 7:30 a.m. to 6:30 p.m., Monday through Thursday, and a police officer has been requested to provide traffic control at the intersection of Kaha Street and Oneawa Street to assist with directing traffic. For the overnight Kailua-bound detour, motorists will be directed to use Kaha Street.

 

North Kalāheo Ave. Bridge Lane Closures/Openings

(Subject to change due to weather and unforeseen conditions)

Days/ Dates

Bridge Traffic

Duration

Weekends/ Holidays

Two-Way Travel

24 hours

Aug 10 – 14

(Mon-Fri)

Extended Contraflow

7:30 a.m. – 6:30 p.m.

Kailua Bound Detour

6:31 p.m. – 7:29 a.m.

Aug 17 – 20

(Mon-Thur)

Contraflow

8:30 a.m. – 3:30 p.m.

Two-Way Travel

3:31 p.m. – 8:29 a.m.

Aug 24 – 28

(Mon-Fri)

Contraflow

8:30 a.m. – 3:30 p.m.

Two-Way Travel

3:31 p.m. – 8:29 a.m.

Aug 31 – Sept 4

(Mon-Fri)

Extended Contraflow

7:30 a.m. – 6:30 p.m.

Kailua Bound Detour

6:31 p.m. – 7:29 a.m.

Sept 8 – 11

(Tue-Fri)

Contraflow

8:30 a.m. – 3:30 p.m.

Two-Way Travel

3:31 p.m. – 8:29 a.m.

Sept 14 – 18

(Mon-Fri)

Extended Contraflow

7:30 a.m. – 6:30 p.m.

Kailua Bound Detour

6:31 p.m. – 7:29 a.m.

Work originally began on March 30, 2026, but sheet pile installation was paused due to a utility clearance issue. After coordination with the utility company, sheet pile installation is scheduled to resume on Monday, August 10, 2026, and is expected to take about one week.

Following the sheet pile installation, the contractor will replace the bridge’s concrete topping. This work also requires special traffic control so the concrete can cure properly and reach its required strength. The concrete topping work is scheduled to take place in two phases on the following dates:

Special Traffic Patterns:

An extended daytime contraflow (7:30 a.m. to 6:30 p.m.) and an overnight Kailua-bound detour (6:31 p.m. to 7:29 a.m.) will be in effect for the following dates:

  • 08/10/26 – 08/14/26: Sheet Pile Installation
  • 08/31/26 – 09/04/26: Bridge Concrete Topping (Phase 1)
  • 09/14/26 – 09/18/26: Bridge Concrete Topping (Phase 2)

TheBus

TheBus Route 674 (Kailua-Aikahi) and Route 87 (Windward Express-Kailua) will be affected by the Kailua-bound detour. Bus Stop #3593 (Kalaheo Ave + Kainui Dr) will not be served while the Kailua-bound detour is in place. While the contraflow is in place, all bus stops will be served.

 

For all other remaining work, one lane will operate under contraflow during work hours (Monday – Friday, 8:30 a.m. – 3:30 p.m.), and the bridge will be fully open outside of work hours until the project’s estimated completion in October 2026.

Press Releases

FAQ

Why can't work be performed at night?

Work cannot be performed during nighttime hours because reduced visibility would compromise worker safety, and the work would generate unreasonable noise impacts to the surrounding community. The construction activities involve using hydraulic hammers to drive sheet piles into the stream bed, resulting in significant noise levels.

The heavy equipment required for bridge work cannot practically be moved back and forth daily during the working week. Doing so would introduce safety risks to workers, motorists, and the structure itself, damage the roadway pavement, extend the overall project timeline, and reduce construction efficiency. Traffic control measures, including lane configurations, are determined by site conditions, safety requirements, and the nature of the ongoing work — not solely by whether active construction is occurring at a given moment.

Pedestrian and school-area safety were central considerations in scheduling this work. By timing the primary construction phase to coincide with the end of the school year and summer recess, we aimed to minimize school-related traffic impacts during the most intensive construction period.

Consideration was given to detouring traffic to allow Kāneʻohe-bound traffic in the mornings and Kailua-bound traffic in the afternoons or evenings during the work week. To route Kailua-bound traffic over the bridge, a detour would need to divert Kāneʻohe-bound motorists off North Kalāheo Avenue by turning left onto Kainui Drive, just past the intersection with L’Orange Place. This presents two significant problems:

Castle Point / Kailuana Place Residents. Approximately 100–200 homes in the Castle Point neighborhood, accessed via Kailuana Place and adjacent side streets, would be restricted to left turns only onto North Kalāheo Avenue under this configuration. There is no practical way to enforce or prevent residents from turning right, making this detour difficult to control safely. It would also significantly increase traffic congestion for drivers exiting streets on the makai side north of L’Orange Place.

Pali Palms Plaza Access. The detour would eliminate access to the Pali Palms Plaza parking lot fronting North Kalāheo Avenue for businesses and Nico’s Restaurant. This parking lot has a Kāneʻohe-bound traffic entrance only, which would be detoured to Kainui Drive. A left turn from the Kailua-bound direction is illegal, and establishing traffic control that effectively compels an illegal maneuver creates unacceptable liability exposure and accident risk.

Traffic impact map for North Kalāheo Avenue bridge work in Kailua showing traffic flow and access changes for Kailua-bound vehicles. North Kalāheo Avenue runs vertically through the center, with Mokapu Road at the top and Kainui Drive near the middle. The bridge work area is highlighted north of Kainui Drive with one lane open at a time. Green arrows indicate Kailua-bound traffic continuing north and detouring west on Kainui Drive, then north on Mokapu Road. Blue arrows indicate Kāneʻohe-bound traffic continuing south on Kalāheo Avenue. Access to Kailuana Place, Private Road, Private Lane, and L’Orange Place is maintained from the south only; northbound entry from Mokapu Road is restricted. A red shaded circle marks the area where traffic congestion is expected near Kainui Drive and the side streets east of Kalāheo Avenue.

Impact of a Kailua-bound only traffic direction